NASA Artemis rocket gets tentative launch dates

Another window for the Artemis launch was requested four days later

NASA said its next Artemis launch attempt could arrive as soon as Sept. 23. 

Engineers are repairing the area where a hydrogen leak was detected during the last attempt last weekend. 

To fix the issue, technicians have set up a protective tent around the work area at Kennedy Space Center's Launch Pad 39B.

They have disconnected the quick disconnect interface for the liquid hydrogen fuel feed line and have begun to replace two seals. 

NASA REPLACING SEAL ON ARTEMIS ROCKET INTERFACE

One seal surrounds the eight-inch line used to fill and drain liquid hydrogen from the core stage, and another surrounds the four-inch bleed line used to redirect some of the propellant during tanking operations. 

Upon completion, engineers will reconnect the plates and perform initial tests to evaluate the new seals. 

No sooner than Sept. 17, the seals will be tested under cryogenic or supercold conditions, during which the Space Launch System rocket's core stage and interim cryogenic propulsion stage will be loaded with liquid oxygen and liquid hydrogen to validate the repair under the conditions it would experience on launch day. 

CLICK HERE TO READ MORE ON FOX BUSINESS

Engineers are in the middle of developing a plan for those checkouts.

The agency has also submitted a request to the Eastern Range for an extension of the current testing requirement for the flight termination system.

It is instructing the Artemis team to move forward with all preparations required for testing. 

GET FOX BUSINESS ON THE GO BY CLICKING HERE

Two launch windows on Sept. 23 and Sept. 27 have been requested, but teams are preparing to support additional dates that align with additional missions.

Load more..